# The East Anglia TWO Offshore Wind Farm Order 2022, Paragraph 1: Application

Extent: E+W+S

(1) For the protection of National Grid, the statutory undertaker referred to in this Part of this Schedule, the following provisions have effect unless otherwise agreed in writing between the undertaker and the statutory undertaker.
(2) Subject to sub-paragraph (3) or to the extent otherwise agreed in writing between the undertaker and the statutory undertakers, where the benefit of this Order is transferred or granted to another person under article 5 (benefit of Order)—
(a) any agreement of the type mentioned in sub-paragraph (1) has effect as if it had been made between the statutory undertaker and the transferee or grantee (as the case may be) in all cases where the transfer of the benefit relates to any specified works; and
(b) written notice of the transfer or grant must be given to the statutory undertaker on or before the date of that transfer or grant.
(3) Without prejudice to paragraph 10(3)(b) below, sub-paragraph (2) does not apply where the benefit of the Order is transferred or granted to the statutory undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2022/433/schedule/10/part/4/paragraph/1 (the official version)
Page: https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-10/part-4/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.