# The East Anglia TWO Offshore Wind Farm Order 2022, Paragraph 8: Details of licensed marine activities

Extent: E+W+S

With respect to any condition which requires the licensed activities be carried out in accordance with the plans, protocols or statements approved under this licence, the approved details, plan or scheme are taken to include any amendments that may subsequently be approved in writing by the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2022/433/schedule/13/part/1/paragraph/8 (the official version)
Page: https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-13/part-1/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.