# The East Anglia TWO Offshore Wind Farm Order 2022, Part 2: Other documents to be certified

Extent: E+W+S

(1)
(2)
(3)
(4)
(5)
Document Reference
Examination Library Reference
Document Name
Version
Date
2.2
REP11-003
Land Plans (onshore)
6
Deadline 11
7th June 2021
2.2.1
AS-002
Land Plans (offshore) (Rev 2)
1
20th December 2019
2.3.1
APP-010
Works Plans (offshore) (Rev 4)
1
25th October 2019
2.3.2
REP11-004
Works Plans (onshore)
7
Deadline 11
7th June 2021
2.4
REP12-004
Access to Works Plan (Rev 2)
2
Deadline 12
28th June 2021
2.5
REP12-005
Temporary Stopping up of Public Rights of Way Plan (Rev 4)
4
Deadline 12
28th June 2021
2.6
REP12-006
Permanent Stopping up of Public Rights of Way Plan (Rev 4)
3
Deadline 12
28th June 2021
2.10
REP12-012
Important Hedgerows and Tree Preservation Order Plan (Rev 4)
4
Deadline 12
28th June 2021
2.12
APP-022
Order limits boundary coordinates plan (offshore)
1
25th October 2019
4.3
REP12-019
Book of Reference (Version 10)
10
Deadline 12
28th June 2021
8.1
. . .
Outline Code of Construction Practice
(Version 10)
10
31 January 2022
8.4
AS-116
Outline Public Rights of Way Strategy
3
22nd April 2021
8.5
REP6-005
Outline Written Scheme of Investigation (Onshore Archaeology)
3
Deadline 6
24th February 2021
8.6
REP3-028
Outline Written Scheme of Investigation (Offshore)
2
Deadline 3
15th December 2020
8.7
. . .
Outline Landscape and Ecological Management Strategy (Version 08)
8
Deadline 13
31 January 2022
8.9
REP11-017
Outline Construction Traffic Management Plan
6
Deadline 11
7th June 2021
8.10
REP12-023
Outline Access Management Plan (Version 07)
7
Deadline 12
28th June 2021
8.11
REP11-022
Outline Travel Plan
6
Deadline 11
7th June 2021
8.12
REP7-027
Outline Offshore Operations and Maintenance Plan
3
Deadline 7
4th March 2021
8.13
REP8-027
Offshore In Principle Monitoring Plan
4
Deadline 8
25th March 2021
8.14
REP8-029
Draft Marine Mammal Mitigation Protocol
4
Deadline 8
25th March 2021
8.17
REP8-031
In Principle East Anglia TWO Project Southern North Sea SAC Site Integrity Plan
4
Deadline 8
25th March 2021
8.18
APP-595
Outline Navigation Monitoring Strategy
1
25th October 2019
8.20
REP1-019
Outline pre-commencement archaeology execution plan (onshore)
2
Deadline 1
2nd November 2020
ExA.AS-1.D12.V4
REP12-025
Outline Landfall Construction Method Statement (Version 04)
4
Deadline 12
28th June 2021
ExA.AS-2.D12.V3
REP12-027
Outline SPA Crossing Method Statement (Version 03)
3
Deadline 12
28th June 2021
ExA.AS-6.D8.V2
REP8-086
Outline Sizewell Gap Construction Method Statement
2
Deadline 8
25th March 2021
ExA.AS-5.D3.V2
REP3-050
Outline Fisheries Liaison and Coexistence Plan
2
Deadline 3
15th December 2020
ExA.AS-4.D6.V3
REP6-039
Outline Sabellaria Reef Management Plan
3
Deadline 6
24th February 2021
ExA.AS-13.D13.V7
REP13-020
Outline Operational Drainage Management Plan (Version 07)
7
Deadline 13
5th July 2021
ExA.AS- 5.D12.V5
REP12-062
Outline Port Construction Traffic Management and Travel Plan
5
Deadline 12
28th June 2021
ExA.AS- 29.D11.V4
REP11-074
Outline Watercourse Crossing Method Statement
4
Deadline 11
7th June 2021
ExA.AS-12.D8.V3
REP8-036
Best Practice Protocol for Minimising Disturbance to Red-Throated Diver
3
Deadline 8
25th March 2021
ExA.AS-6.D11.V4
AS-133
Substations Design Principles Statement (Rev 04)
4
...
21st June 2021
ExA.AS-6.SoSQ2.V5
. . .
Offshore Ornithology Without Prejudice Compensation Measures
5
31 January 2022
ExA.AS-35.D8.V2
REP8-077
Activity Exclusion Zones Plan
2
Deadline 8
25th March 2021
ExA.AS-15.D7.V1
REP7-037
Sizewell C Order Limits Interaction – Offshore Plan
1
Deadline 7
4th March 2021
ExA.AS-34. D9.V2
REP9-031
Layout Principles Statement
2
Deadline 9
15th April 2021

---
Source: https://www.legislation.gov.uk/uksi/2022/433/schedule/17/part/2 (the official version)
Page: https://openlegislation.uk/east-anglia-two-offshore-wind-farm-order-2022/schedule-17/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.