# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 15: Building sustainability

Extent: E+W+S

(1) No development of a warehouse may take place until a BREEAM Pre-Assessment Report based upon the BREEAM 2011 method (or equivalent) has been submitted to and approved in writing by the local planning authority demonstrating that the unit is expected to achieve at least a BREEAM 2011 “Very Good” rating (BREEAM Industrial 2008 “Excellent”).
(2) The development of each of the warehouses must be carried out in accordance with the details in the BREEAM Pre-Assessment Report (or equivalent) for that unit and a certificate must be provided within three months of completion or occupation (whichever is the sooner) of each warehouse confirming that the measures in respect of that warehouse committed to within the Pre-Assessment Report have been implemented.

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/east-midlands-gateway-rail-freight-interchange-and-highway-order-2016/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.