# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 2: Phases of development

Extent: E+W+S

(1) No phase of the authorised development (with the exception of the highway works which are governed by requirements 4 and 5 and Schedules 19 and 20 (protection of interests)) is to commence until a written scheme setting out all the phases of the authorised development which must be in accordance with the approach to phasing set out in the construction management framework plan (Document 6.10) and the schedule of archaeological works (Document 6.24), has been submitted to and approved in writing by the local planning authority. The written scheme must include phasing details of—
(a) earthworks;
(b) ecological mitigation;
(c) rail infrastructure;
(d) roads within the main site;
(e) surface water and foul drainage;
(f) development plots;
(g) landscaping; and
(h) mains services.
(2) The authorised development must be carried out in accordance with the phasing as approved in writing by the local planning authority.
(3) The rail terminal constructed as part of Works No. 2 must be constructed and available for use prior to the occupation of more than 260,000square metres of the rail served warehousing.

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/2/paragraph/2 (the official version)
Page: https://openlegislation.uk/east-midlands-gateway-rail-freight-interchange-and-highway-order-2016/schedule-2/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.