# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 20: Construction hours

Extent: E+W+S

(1) Subject to sub-paragraph (2) construction and demolition works (which for the purposes of this requirement excludes archaeological investigations, landscaping works and any non-intrusive internal fit-out works but must include start up and shut down and deliveries) must not take place other than between 07:30 and 19:00 hours on weekdays and 08:00 and 13:00 hours on Saturdays, excluding public holidays, unless otherwise agreed in writing by the local planning authority. Outside the above periods the following working is permitted:
(a) pre-planned construction works to highway or rail infrastructure requiring possessions where first notified to the local planning authority and local residents;
(b) emergency works; and
(c) works which do not cause noise that is audible at the boundary of the Order Limits.
(2) Regardless of sub-paragraph (1) no piling operations are to take place after 18:00 hours unless otherwise agreed in writing by the local planning authority.
(3) Any emergency works carried out under sub-paragraph (1)(b) must be notified to the local planning authority within 72 hours of their commencement.

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/2/paragraph/20 (the official version)
Page: https://openlegislation.uk/east-midlands-gateway-rail-freight-interchange-and-highway-order-2016/schedule-2/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.