# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 26: Waste management during the operational phase

Extent: E+W+S

No part of the authorised development may be brought into use until a scheme for waste management has been submitted to and approved in writing by the local planning authority. Thereafter the approved scheme must be implemented and maintained for the duration of the operation of the development.

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/2/paragraph/26 (the official version)
Page: https://openlegislation.uk/east-midlands-gateway-rail-freight-interchange-and-highway-order-2016/schedule-2/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.