# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 5: Design and phasing of highways works

Extent: E+W+S

The undertaker must use reasonable endeavours to complete the highway works identified in column (1) of the table below by no later than the stage of development set out in column (3) of the table below or such alternative later triggers as are agreed by the relevant body identified in column (4) and the local planning authority.
Highway Works
(1)
Item as identified on the highway works components plans (Document 2.13)
(2)
Description
(3)
Stage of Development
(4)
Relevant Body
(i)
A453 site access and
Kegworth Bypass Junction (not including the bypass itself).
To be completed prior to the occupation of first warehouse to be occupied.
Highways England
(ii)
A50 eastbound to M1 southbound and Junction 24 interchange links; M1 southbound to A50 interchange link; improvements to M1 southbound from Junction 24A to Junction 24; and alterations to Junction 24 roundabout east of M1.
To be completed prior to the occupation of first warehouse to be occupied.
Highways England
(iii)
Construction of local access road to Lockington.
To be completed prior to the occupation of first warehouse to be occupied.
Leicestershire County Council
(iv)
Diseworth Lane alterations.
To be completed prior to the occupation of the first warehouse to be occupied.
Leicestershire County Council
(v)
Church Street works.
To be completed prior to the occupation of the first warehouse to be occupied.
Leicestershire County Council
(vi)
Alterations to Junction 24 roundabout west of M1; improvements to A50 and A453 west of M1; and alterations to M1 northbound exit slip road.
To be completed prior to the occupation of the first warehouse to be occupied.
Highways England
(vii)
Kegworth Bypass including alterations to Ashby Road and Whatton Road.
To be completed prior to the occupation of more than 185,800 square metres (gross internal area) of warehouse floorspace.
Leicestershire County Council
(viii)
M1 overbridges from Ashby Road to A453 and from Kegworth Bypass to A453.
To be completed prior to the occupation of more than 185,800 square metres (gross internal area) of warehouse floorspace.
(1) Highways England (bridge structures)
(2) Leicestershire County Council (highway)
(ix)
Warren Lane access and public footpath and cycle track adjacent to A50 interchange links connecting Warren Lane and A453 eastbound.
To be completed prior to the occupation of the first warehouse to be occupied.
Leicestershire County Council

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/east-midlands-gateway-rail-freight-interchange-and-highway-order-2016/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.