The undertaker must permit and must require any contractor or sub-contractor engaged on the highway works to permit at all reasonable times persons authorised by the highway authority whose identity has been previously notified to the undertaker to gain access to the site of the highway works for the purpose of inspection to verify compliance with the provisions of this Schedule in accordance with the highway authority’s inspection policy.

---