# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 3: Highway works

Extent: E+W+S

The undertaker must carry out and complete the highway works in accordance with—
(a) the detailed design information approved under paragraph 14; and
(b) the programme of works approved under paragraph 22 or as subsequently varied by agreement between the undertaker and the highway authority.

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/20/paragraph/3 (the official version)