# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 9: Security

Extent: E+W+S

Prior to the commencement of each phase of the highway works the undertaker must secure the cost of it by the deposit with the highway authority of a bond, drafted substantially as detailed in Form 2 contained in paragraph 10, in a sum equivalent to the director’s reasonable estimate of the cost of that phase of the highway works (including any statutory undertakers works) or must provide some alternative form of security acceptable to the highway authority.

---