# The East Midlands Gateway Rail Freight Interchange and Highway Order 2016, Paragraph 3

Extent: E+W+S

The undertaker must before commencing construction of any specified work supply to Tarmac copies of the detailed design information in relation to that work approved by the relevant highway authority under the provisions of Schedules 19 and 20 (protection of interests).

---
Source: https://www.legislation.gov.uk/uksi/2016/17/schedule/21/paragraph/3 (the official version)
Page: https://openlegislation.uk/east-midlands-gateway-rail-freight-interchange-and-highway-order-2016/schedule-21/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.