# The East Northamptonshire Resource Management Facility Order 2013, Article 7: Certification of plans etc

Extent: E+W+S

(1) The undertaker shall, as soon as practicable after the making of this Order, submit to the Secretary of State copies of the following plans and documents—
(a) the land plan (WS010001/ENRMF/PLANS/LAND);
(b) the works plan (WS010001/ENRMF/PLANS/WORKS);
(c) Elevations of main infrastructure including buildings (WS010001/ENRMF/PLANS/ELEVATION3);
(d) The site access from Stamford Road (WS010001/ENRMF/PLANS/ELEVATION4);
(e) Proposed post-settlement restoration contours (WS010001/ENRMF/PLANS/ELEVATION1);
(f) Elevations of the infrastructure associated with the soil treatment plant (WS010001/ENRMF/PLANS/ELEVATION5);
(g) Elevations of the stockpiles and bunds (WS010001/ENRMF/PLANS/ELEVATION2);
(h) figure ES6 of the environmental document;
(i) the Biodiversity Action Plan for East Northants RMF at appendix 3 of appendix ESF to the environmental document;
(j) the Restoration Scheme (WS010001/ENRMF/PLANS/SITE1);
(k) the transport assessment at appendix ESJ to the environmental document (WS010001/ENRMF/ESAPPESJ);
(l) figures ES10A to ES10J of the environmental document;
(m) the environmental document;
(n) Noise management and monitoring scheme (WS010001/ENRMF/ESAPPESE);
(o) the current permits for the landfill site (EPR/TP3430GW) and the soil treatment plant (YP3138XB); and
(p) any other plans or documents referred to in this Order,
for certification that they are true copies of the documents referred to in this Order.
(2) A plan or document so certified shall be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

---
Source: https://www.legislation.gov.uk/uksi/2013/1752/article/7 (the official version)