# The East Yorkshire Solar Farm Order 2025, Paragraph 42: As built drawings

Extent: E+W

(1) As soon as reasonably practicable following the completion of the construction of the authorised development, the undertaker must provide to the Canal & River Trust as built drawings of any specified works in a form and scale to be agreed between the undertaker and the Canal & River Trust to show the position of those works in relation to the waterway.

---
Source: https://www.legislation.gov.uk/uksi/2025/585/schedule/14/paragraph/42 (the official version)
Page: https://openlegislation.uk/east-yorkshire-solar-farm-order-2025/schedule-14/paragraph-42
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

