  "heading": "Interaction with the SEGL2 Project",
  "text": "(1) Without limiting any other provision of this Part of this Schedule, the undertaker must use reasonable endeavours to avoid any conflict arising between the construction, maintenance and operation of the authorised development and the SEGL2 Project. For the purposes of this paragraph, “reasonable endeavours” means—\n(a) undertaking consultation on the detailed design and programming of the National Grid connection works and all works associated with or ancillary to the National Grid connection works to ensure that the design and programme for the National Grid connection works does not unreasonably impede or interfere with the SEGL2 Project;\n(b) undertaking consultation on the detailed design and programming of the Solar array works and all works associated with or ancillary to the Solar array works to ensure that the design and programme for the Solar array works does not unreasonably impede or interfere with the SEGL2 Project;\n(c) having regard to the proposed programme of works for the SEGL2 Project as may be made available to the undertaker by National Grid and facilitating a co-ordinated approach to the programme, land assembly, and the carrying out of the National Grid connection works and the SEGL2 Project;\n(d) providing a point of contact for continuing liaison and co-ordination throughout the construction and operation of the authorised development; and\n(e) keeping National Grid informed on the programme of works for the authorised development.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 14 para. 80 in force at 31.5.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/585/schedule/14/paragraph/80",
    "retrieved_at": "2026-10-28T21:15:59.558746+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}