# The East Yorkshire Solar Farm Order 2025, Paragraph 12: Operational environmental management plan

Extent: E+W

(1) Prior to the date of final commissioning for any part, an operational environmental management plan for that part must be submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of both East Riding of Yorkshire Council and North Yorkshire Council, both relevant planning authorities. Such approval to be in consultation with Natural England, as well as the Environment Agency and the lead local flood authority where the operational environmental management plan is affected by an updated version of the flood risk assessment.
(2) The operational environmental management plan must be substantially in accordance with the framework operational environmental management plan and must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2025/585/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/east-yorkshire-solar-farm-order-2025/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.