# The East Yorkshire Solar Farm Order 2025, Paragraph 3: Approved details and amendments to them

Extent: E+W

(1) With respect to the documents certified under article 40 (certification of plans and documents, etc.) and any plans, details or schemes which have been approved pursuant to any requirement (together the “Approved Documents, Plans, Details or Schemes”), the undertaker may submit to the relevant planning authority or both relevant planning authorities (as applicable) for approval of any amendments to any of the Approved Documents, Plans, Details or Schemes and, following approval by the relevant planning authority or both relevant planning authorities (as applicable), the relevant Approved Documents, Plans, Details or Schemes is to be taken to include the amendments as so approved pursuant to this paragraph.
(2) Approval under sub-paragraph (1) for the amendments to any of the Approved Documents, Plans, Details or Schemes must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority or both relevant planning authorities (as applicable) that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
(3) Where under any of the requirements the approval, agreement or confirmation of the relevant planning authority or both relevant planning authorities is required, that approval, agreement or confirmation must be provided in writing.
(4) Within 14 days of the date of final commissioning the undertaker must serve written notice of the date of final commissioning on both relevant planning authorities.

---
Source: https://www.legislation.gov.uk/uksi/2025/585/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/east-yorkshire-solar-farm-order-2025/schedule-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.