# The East Yorkshire Solar Farm Order 2025, Paragraph 5: Detailed design approval

Extent: E+W

(1) No part of the authorised development may commence until details of—
(a) layout;
(b) scale;
(c) proposed finished ground levels;
(d) external appearance;
(e) hard surfacing materials;
(f) vehicular and pedestrian access, parking and circulation areas; and
(g) refuse or other storage units, signs and lighting.
relating to that part have been submitted and approved in writing by the relevant planning authority for that part or, where the part falls within the administrative areas of both East Riding of Yorkshire Council and North Yorkshire Council, both relevant planning authorities.
(2) The details submitted must accord with the outline design principles statement.
(3) The authorised development must be carried out in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2025/585/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/east-yorkshire-solar-farm-order-2025/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.