# The East Yorkshire Solar Farm Order 2025, Paragraph 6: Landscape and Ecological management plan

Extent: E+W

(1) No part of the authorised development may commence until a written landscape and ecological management plan has been submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of both East Riding of Yorkshire Council and North Yorkshire Council, both relevant planning authorities. Such approval to be in consultation with Natural England.
(2) The landscape and ecological management plan must be substantially in accordance with the framework landscape and ecological management plan and must be implemented as approved.
(3) For the purposes of sub-paragraph (1), “commence” includes part (h) (site clearance (including vegetation removal, demolition of existing buildings and structures)) and part (i) (advanced planting to allow for an early establishment of protective screening) of permitted preliminary works.

---
Source: https://www.legislation.gov.uk/uksi/2025/585/schedule/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/east-yorkshire-solar-farm-order-2025/schedule-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.