An authority shall publish in the manner set out in regulation 4—

(a)

the inspection report relating to it within 30 working days, or where (in the case of an authority in Wales) a translation into Welsh or English is also being published, 40 working days; and

(b)

its action plan within 70 working days, or where (in the case of an authority in Wales) a translation into Welsh or English is also being published, 80 working days,

of the receipt by it of a copy of the inspection report under section 39(1) of the Act.