Regulation 7 Reports and action plans
An inspection shall be carried out during a period not exceeding two weeks.
The registered inspector shall, within five weeks from the completion of the inspection, prepare in writing a report of the inspection and a summary of the report.
The appropriate authority shall, within forty working days from the date when the registered inspector reported to them, prepare an action plan.
The appropriate authority shall, within five working days from the date when they completed the preparation of the action plan, send copies of it to the persons and bodies mentioned in paragraph 10(2) of Schedule 2 to the Act, to all persons employed at the school and, in the case of a secondary school, the Training and Enterprise Council for the area in which the school is located.