OpenLegislation

Regulation 6 Reports and action plans

Original text. Later amendments are not shown.

(1)

An inspection shall be carried out during a period not exceeding two weeks.

(2)

Within five weeks from the completion of the inspection, or within seven weeks thereof where it is necessary to provide a translation into Welsh or English, the registered inspector shall prepare in writing a report of the inspection and a summary of the report.

(3)

The appropriate authority shall, within forty working days from the date when the registered inspector reported to them or within 45 working days thereof where it is necessary to provide a translation into Welsh or English, prepare an action plan.

(4)

The appropriate authority shall, within five working days from the date when they completed the preparation of the action plan, send copies of it together with any translation thereof to the persons and bodies mentioned in paragraph 10(2) of Schedule 2 to the Act and to all persons employed at the school and in the case of a secondary school, the Training and Enterprise Council for the area in which the school is located.