# The Eggborough Gas Fired Generating Station Order 2018, Paragraph


Work No. 3 – electrical connection works comprising—
(g) Work No. 3A – up to 400 kilovolt underground electrical cables and control systems cables to and from the existing National Grid substation; and
(h) Work No. 3B – works within the existing National Grid substation, including underground and over ground cables, connections to busbars and new, upgraded or replacement equipment.

---
Source: https://www.legislation.gov.uk/uksi/2018/1020/schedule/1/paragraph/wrapper5n1 (the official version)
Page: https://openlegislation.uk/eggborough-gas-fired-generating-station-order-2018/schedule-1/paragraph-wrapper5n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.