# The Eggborough Gas Fired Generating Station Order 2018, Paragraph 19: Fencing


Where so required by the engineer the undertaker must to the reasonable satisfaction of the engineer fence off a specified work or a protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from the waterway, whether on a temporary or permanent basis or both.

---
Source: https://www.legislation.gov.uk/uksi/2018/1020/schedule/12/paragraph/19 (the official version)