# The Eggborough Gas Fired Generating Station Order 2018, Paragraph 15: Contaminated land and groundwater


(1) No part of the authorised development may commence, save for geotechnical surveys and other investigations for the purpose of assessing ground conditions, until a scheme to deal with the contamination of land, including groundwater, which is likely to cause significant harm to persons or pollution of controlled waters or the environment, has, for that part, been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.
(2) The scheme submitted and approved must be in accordance with the principles set out in chapter 12 of the environmental statement and the environmental statement commitments register and must be included in the construction environmental management plan submitted pursuant to requirement 18.
(3) The scheme must include a risk assessment, supported by site investigation data, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a materials management plan, which sets out long-term measures with respect to any contaminants remaining on the site.
(4) The authorised development, including any remediation, must be carried out in accordance with the approved scheme unless otherwise agreed with the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2018/1020/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/eggborough-gas-fired-generating-station-order-2018/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.