# The Eggborough Gas Fired Generating Station Order 2018, Paragraph 33: Local liaison committee


(1) No part of the authorised development may commence, save for the permitted preliminary works, until the undertaker has established a committee to liaise with local residents and organisations about matters relating to the authorised development (a ‘local liaison committee’).
(2) The undertaker must invite the relevant planning authority and other relevant interest groups, as may be agreed with the relevant planning authority, to nominate representatives to join the local liaison committee.
(3) The undertaker must provide a full secretariat service and supply an appropriate venue for the local liaison committee meetings to take place.
(4) The local liaison committee must—
(a) include representatives of the undertaker;
(b) meet every other month, starting in the month prior to commencement of the authorised development, until the completion of construction, testing and commissioning works unless otherwise agreed by the majority of the members of the local liaison committee; and
(c) during the operation of the authorised development meet once a year unless otherwise agreed by the majority of the members of the local liaison committee.

---
Source: https://www.legislation.gov.uk/uksi/2018/1020/schedule/2/paragraph/33 (the official version)