# The Electricity Act 1989 (Exemption from the Requirement for a Generation Licence) (Gunfleet Sand) (England and Wales) Order 2007, Article 4: Conditions on exemption


The exemption granted by article 3 to Gunfleet is subject to compliance with the following conditions—
(a) that Gunfleet does not hold a licence under section 6(1)(a) of the Act (licence authorising generation of electricity for supply);
(b) that Gunfleet Sands Wind Farm is connected to the total system in England and Wales and (except in circumstances outside the reasonable control of Gunfleet) does not export more than 100 megawatts of electrical power to it at any time.

---
Source: https://www.legislation.gov.uk/uksi/2007/990/article/4 (the official version)
Page: https://openlegislation.uk/electricity-act-1989-exemption-from-the-requirement-for-a-generation-licence-gunfleet-sand-england-and-wales-order-2007/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.