# Electricity Act 1989, Paragraph 1

Extent: E+W+S+N.I.

The following are relevant provisions in relation to all licence holders (except the holder of a smart meter communication licence or a code manager licence)—
(a) sections 32 to 32M;
(b) section 42C;
(c) section 25(5) of the Consumers, Estate Agents and Redress Act 2007 (directions to comply with requirements under section 24 of that Act);
(ca) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(d) in the Electricity Regulation—
(i) Article 50(5) (provision of information relating to the transmission system etc),
(ii) Article 16(10) and (12) (duties relating to intended use of capacity);
(e) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(f) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(g) in the Transparency Regulation—
(i) Article 4 (submission and publication of data),
(ii) Article 6 (information on total load),
(iii) Article 7 (information relating to the unavailability of consumption units),
(iv) Article 8 (year-ahead forecast margin),
(v) Article 9 (transmission infrastructure),
(vi) Article 10 (information relating to the unavailability of transmission infrastructure),
(vii) Article 11 (information relating to the estimation and offer of cross zonal capacities),
(viii) Article 12 (information relating to the use of cross zonal capacities),
(ix) Article 13 (information relating to congestion management measures),
(x) Article 14 (forecast generation),
(xi) Article 15 (information relating to the unavailability of generation and production units),
(xii) Article 16 (actual generation),
(xiii) Article 17 (balancing).

---
Source: https://www.legislation.gov.uk/ukpga/1989/29/schedule/6A/paragraph/1 (the official version)
Page: https://openlegislation.uk/electricity-act-1989/schedule-6A/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.