# The Electricity and Gas Appeals (Designation and Exclusion) Order 2014, Article 4: Exclusions

Extent: E+W+S

(1) A right of appeal under section 173 of the Act is excluded in respect of a decision by GEMA relating to a document designated by article 3 if—
(a) in the case of a decision falling within any of articles 5 to 13, the condition specified for that decision is satisfied; or
(b) GEMA determines that the delay caused by the holding of the appeal against that decision is likely to have a material adverse effect on the availability of electricity or gas for meeting the reasonable demands of consumers in Great Britain.
(2) Where GEMA makes a determination under paragraph (1)(b), it must give notice of the determination in such manner as it considers appropriate for the purpose of bringing it to the attention of persons likely to be interested in it.

---
Source: https://www.legislation.gov.uk/uksi/2014/1293/article/4 (the official version)
Page: https://openlegislation.uk/electricity-and-gas-appeals-designation-and-exclusion-order-2014/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.