# The Electricity and Gas Appeals (Designation and Exclusion) Order 2014, Article 6: Connection and Use of System Code

Extent: E+W+S

(1) For a decision relating to the Connection and Use of System Code, the specified condition is that the decision consists in the giving of a consent to a majority recommendation of Panel Members in the Modification Report.
(2) In this article—
(a) “majority recommendation” means a recommendation that is supported by the majority of those views of Panel Members which, in the reasonable opinion of GEMA, are clearly expressed in the Modification Report; and
(b) the words “Panel Members” and “Modification Report” have the same meanings as in the Connection and Use of System Code.

---
Source: https://www.legislation.gov.uk/uksi/2014/1293/article/6 (the official version)