# The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019, Regulation 125

Extent: E+W+S+N.I.

(1) Article 39B (review of exemptions under Article 39A) is amended as follows.
(2) Omit paragraphs (1) and (2).
(3) In paragraph (4)—
(a) in sub-paragraph (a)—
(i) after “if” insert “ before IP completion day ”;
(ii) after “paragraph (1)” insert “ (as it then had effect) ”;
(b) in sub-paragraph (b), after “if” insert “ before IP completion day ”;
(c) for sub-paragraph (c) substitute—
“(c) if—
(i) before IP completion day the Authority sent the European Commission a copy of the exemption and terms under paragraph (1) (as it then had effect), and
(ii) the European Commission does not act as described in paragraph (a) or (b) before IP completion day,
the date four months after the Authority sent the European Commission a copy of the exemption under paragraph (1) or IP completion day, whichever is the sooner;
(d) if the decision to give the exemption was published under Article 39A(12) on or after IP completion day, the date on which the decision was published under Article 39A(12).”.

---
Source: https://www.legislation.gov.uk/uksi/2019/530/regulation/125 (the official version)