# The Electricity and Gas (Standards of Performance) (Suppliers) Regulations 2015, Regulation 12: Amendment of the Gas (Standards of Performance) Regulations 2005

Extent: E+W+S

The Gas (Standards of Performance) Regulations 2005 are amended as follows—
(a) in regulation 3 (interpretation)—
(i) for the definition of “relevant operator” substitute—
““relevant operator” means the relevant gas transporter or the gas transporter according to the circumstances of the relevant customer’s case;”
(ii) omit the definitions of “appropriate meter”, “margins of error” and “specified time”;
(b) for the heading of Part 2 (Gas supplier’s and gas transporter’s individual standards of performance), substitute “Gas transporter’s individual standards of performance”;
(c) omit regulations 4, 5, 6, 12(1) and (3), 14, 15(1), (3) and (4) and 16;
(d) in regulation 13(4) (exemptions), for the words “regulation 6(1) or 10(1)(d)”, substitute “regulation 10(1)(d)”;
(e) for the heading of Schedule 1, Part 1 (Prescribed periods and prescribed sums applicable to all gas suppliers and gas transporters), substitute “Prescribed Periods and Prescribed Sums Applicable to all Gas Transporters”; and
(f) in Schedule 1, Part 1, omit the entries in the table in relation to regulations 4(2), (4)(a) and (4)(b), 5(3), 6(2) and (3) and 12(3).

---
Source: https://www.legislation.gov.uk/uksi/2015/1544/regulation/12 (the official version)
Page: https://openlegislation.uk/electricity-and-gas-standards-of-performance-suppliers-regulations-2015/regulation-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.