# The Electricity and Gas (Standards of Performance) (Suppliers) Regulations 2015, Regulation 6ZA: Obligation to complete a supplier transfer


(1) This regulation applies where a customer requests a supplier transfer.
(2) This regulation does not apply where the supplier transfer cannot be completed because—
(a) the customer notifies the new supplier that they do not wish the supplier transfer to take place;
(b) a previous supplier transfer is being processed in relation to the same meter point; or
(c) the customer’s current supplier objects to the supplier transfer.
(3) Where this regulation applies the new supplier must complete the supplier transfer—
(a) where the customer has requested that the new supplier begin the supply before the end of the cooling off period, within the period of 5 working days beginning with the day of receipt by the new supplier of sufficient information to—
(i) confirm the supplier transfer relates to the customer who requested it, and
(ii) identify the meter point or meter points to which the supplier transfer request relates;
(b) where the customer has requested a supplier transfer takes place on a date after the end of the period referred to in sub-paragraph (a), on the date requested; ...
(c) where the customer has existing debt on a prepayment meter and the new supplier agrees to be assigned that debt, within the period of 15 working days beginning with the day of that assignment being agreed between the old and new supplier, but no later than 32 working days from receipt by the new supplier of the information in sub-paragraph (a)(i) and (ii) or,
(d) where the customer has not requested that the new supplier begin the supply before the end of the cooling off period, within the period of 5 working days beginning with the day on which the latest of the following events occurs—
(i) receipt by the new supplier of sufficient information to confirm the supplier transfer relates to the customer who requested it,
(ii) receipt by the new supplier of sufficient information to identify the meter point or meter points to which the supplier transfer request relates, and
(iii) expiry of the period of 14 days beginning with the day on which the customer and new supplier entered into the contract.
(4) In this regulation—
(a) where the customer enters into a contract with the new supplier after 5pm on a working day, a reference to “5 working days” is to be read as “6 working days”; and
(b) “cooling off period” means the period of time after entering into a contract with a new supplier within which that customer may cancel the contract in accordance with any relevant contractual term or applicable statutory provision.

---
Source: https://www.legislation.gov.uk/uksi/2015/1544/regulation/6ZA (the official version)
Page: https://openlegislation.uk/electricity-and-gas-standards-of-performance-suppliers-regulations-2015/regulation-6ZA
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.