# The Electricity and Gas (Standards of Performance) (Suppliers) Regulations 2015, Regulation 6ZB: Avoidance of erroneous transfers


(1) This regulation applies where a new supplier proposes to complete a supplier transfer.
(2) This regulation does not apply where a customer is transferred to a supplier appointed by the Authority following a last resort supply direction being given within 21 working days of an agreement reached in accordance with regulation 6C(1)(b).
(3) Where this regulation applies the new supplier must only complete a supplier transfer where there is a valid contract with the customer who is subject to the supplier transfer.
(4) For the purposes of this regulation, failure to meet the standard of performance in paragraph (3) is determined when the old supplier and the new supplier have agreed that the customer has been transferred without a valid contract.

---
Source: https://www.legislation.gov.uk/uksi/2015/1544/regulation/6ZB (the official version)
Page: https://openlegislation.uk/electricity-and-gas-standards-of-performance-suppliers-regulations-2015/regulation-6ZB
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.