# The Electricity (Applications for Licences and Extensions and Restrictions of Licences) Regulations 2001, Paragraph 2


Provide a statement of—
(a) the number of generating stations to be operated;
(b) a description of how each of those stations will, in each case, be fuelled or driven;
(c) the date when any proposed generating stations are expected to be commissioned;
(d) the maximum power (MW) for each of the next five years expected to be available from each generating station at any one time and the aggregate power (MW) expected to be available from each generating station during any year (Exclude (in each case) such wattage as is expected to be consumed at the station);
(e) the expected life of each generating station;
(f) for each generating station for each of the next five years, the numbers of generating units and the capacity of each generating unit; and
(g) particulars of the person or persons to whom the applicant intends for each of the next five years to provide electricity and particulars of the distribution of that electricity, including details of the lines to be constructed.

---
Source: https://www.legislation.gov.uk/uksi/2001/3354/schedule/3/part/I/paragraph/2 (the official version)
Page: https://openlegislation.uk/electricity-applications-for-licences-and-extensions-and-restrictions-of-licences-regulations-2001/schedule-3/part-I/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

