An outline statement of the business proposals, for that business of the applicant to which the application relates, for the next five years which includes:

(i)

particulars of the person or persons from whom, and the points at which, the applicant expects to receive the electricity which he will transmit; particulars of transmission of the electricity; particulars of the expected points of off-take; and quantities;

(ii)

interconnections to other transmission systems;

(iii)

proposed metering arrangements;

(iv)

schedule of generating plant owned by the applicant including:–

  • pumped storage

  • clutched gas turbine generators/synchronous compensators

(v)

forecast annual maximum demands in his transmission system (GW) and energy (GWh) to be transmitted;

(vi)

summary large scale map, together with detailed maps providing information on areas where activities are concentrated as necessary;

(vii)

a single line diagram of the transmission system should be provided. All transmission voltage levels (400 and 275 kV in England and Wales and 400, 275 and 132 kV in Scotland) should be shown on the diagram;

(viii)

annual forecasts of costs, sales and revenues and project financing, stating the assumptions underlying the figures provided.