OpenLegislation

Paragraph 2

Original text. Later amendments are not shown.

An outline statement of the business proposals, for that business of the applicant to which the application relates, for the next five years which includes:

(i)

particulars of the person or persons to whom the applicant intends to provide electricity and particulars of the distribution of that electricity, including details of lines to be constructed;

(ii)

the maximum power (MW) expected to be available from each generating station at any one time. The aggregate power (MW) expected to be available from each generating station during any year. Exclude (in each case) such wattage as is expected to be consumed at the station;

(iii)

the expected life of each generating station;

(iv)

for each generating station, the numbers of generating units and the capacity of each generating unit;

(v)

map or maps sufficient to identify the location of all generating stations to which the application relates; and

(vi)

annual forecasts of costs, sales and revenues and project financing, stating the assumptions underlying the figures provided.