# The Electricity (Applications for Licences, Modifications of an Area and Extensions and Restrictions of Licences) (No. 2) Regulations 2004, Paragraph 1


An application in respect of a interconnector licence must specify the actual or proposed point of connection to an electricity transmission or electricity distribution network. Where the applicant is unable to specify a point of connection the applicant should provide Ordnance Survey Grid Reference co-ordinates for the proposed point of connection.

---