# The Electricity Capacity (Amendment etc.) (Coronavirus) Regulations 2020, Paragraph 1: Regulation 5 (“demand side response CMU”)

Extent: E+W+S

(1) In regulation 5(2)(a)(i), at the beginning insert “subject to paragraph (2A),”.
(2) After regulation 5(2), insert—
“(2A) For the purposes of this regulation, the reference in regulation 5(2)(a)(i) to a “DSR customer’s import of electricity” does not include import of electricity primarily for the conversion of electricity into a form of energy which can be stored by a storage facility.”

---
Source: https://www.legislation.gov.uk/uksi/2020/697/schedule/1/paragraph/1 (the official version)
Page: https://openlegislation.uk/electricity-capacity-amendment-etc-coronavirus-regulations-2020/schedule-1/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.