# The Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2015, Paragraph 1

Extent: E+W+S

The events in this Schedule are—
(a) the Authority determines that there are no bidders or qualifying bidders in respect of a qualifying project;
(b) a developer has been disqualified from a tender exercise in accordance with regulation 27(1);
(c) a developer breaches an undertaking given to the Authority pursuant to paragraph 3 of Schedule 1;
(d) a developer fails to meet the entry conditions specified in paragraph 1 or 2 of Schedule 2, as the case may be, in accordance with regulation 11;
(e) a developer does not agree the variation to the bilateral agreement with the holder of a co-ordination licence in order that the preferred bidder has in place a valid bilateral agreement;
(f) a developer terminates its bilateral agreement with the holder of a co-ordination licence;
(g) a developer withdraws its qualifying project from a tender exercise for any reason;
(h) a developer notifies the Authority that it wishes to change its request made in accordance with regulation 8 by—
(aa) re-specifying whether the project is intended to meet the requirements relating to a generator build qualifying project or an OFTO build qualifying project; or
(bb) notifying a construction phase contract that was not previously notified;
(i) a developer modifies a construction phase contract in such a way that the Authority is no longer satisfied that the terms of the contract are conducive to the development of an efficient, coordinated and economical system of electricity transmission.

---
Source: https://www.legislation.gov.uk/uksi/2015/1555/schedule/8/paragraph/1 (the official version)
Page: https://openlegislation.uk/electricity-competitive-tenders-for-offshore-transmission-licences-regulations-2015/schedule-8/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.