# The Electricity (Connection Standards of Performance) Regulations 2015, Paragraph 1

Extent: E+W+S

(1) This Schedule applies where a dispute to which regulation 13 applies has arisen under any provision of these Regulations between an electricity distributor and a customer or relevant authority (as applicable).
(2) A dispute to which this Schedule applies—
(a) may be referred to the Authority by any party or, with the agreement of any party, by a consumer advocacy body; and
(b) on such reference, is to be determined by order made by the Authority.
(3) In making an order under this Schedule, the Authority must include in the order the reasons for reaching its decision with respect to a dispute.

---
Source: https://www.legislation.gov.uk/uksi/2015/698/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/electricity-connection-standards-of-performance-regulations-2015/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.