# The Electricity (Connection Standards of Performance) Regulations 2015, Paragraph 14

Extent: E+W+S

(1) An order determining a dispute may include a provision requiring the electricity distributor or the customer or the relevant authority (as applicable) to pay a sum in respect of the costs or expenses incurred by the Authority.
(2) In including in an order under sub-paragraph (1) any such provision as to costs, the Authority must have regard to the conduct and means of the parties and any other relevant circumstances.

---
Source: https://www.legislation.gov.uk/uksi/2015/698/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/electricity-connection-standards-of-performance-regulations-2015/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.