# The Electricity (Criteria for Relevant Electricity Projects) (Transmission) Regulations 2024, Article 3: Criteria for projects


(1) Subject to paragraphs (2) to (4), the criteria in regulations 4 to 8 are specified in respect of a project that relates to a transmission system, for the purposes of section 6BA(1)(b) of the Act.
(2) These Regulations do not apply to a project or any part of a project which is or may be subject to determination on a competitive basis of the person to whom an offshore transmission licence is to be granted under the Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2015.
(3) The criterion in regulation 7 applies only to early-model tender exercises.
(4) The criterion in regulation 8 applies only to late-model tender exercises.

---
Source: https://www.legislation.gov.uk/uksi/2024/168/article/3 (the official version)
Page: https://openlegislation.uk/electricity-criteria-for-relevant-electricity-projects-transmission-regulations-2024/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.