# The Electricity (Criteria for Relevant Electricity Projects) (Transmission) Regulations 2024, Article 4: Network Need criterion


A project’s electricity solution must be capable, with reasonable certainty, of addressing a network need.

---
Source: https://www.legislation.gov.uk/uksi/2024/168/article/4 (the official version)
Page: https://openlegislation.uk/electricity-criteria-for-relevant-electricity-projects-transmission-regulations-2024/article-4