Article 8 High value criterion in respect of a late-model tender exercise
A project must have an estimated capital expenditure equal to or greater than £100,000,000.
In this regulation “estimated capital expenditure” means an estimate of the total costs of a project, calculated by reference to one or more of the following—
any costs relating to the purchase of component parts;
construction costs;
the costs of the acquisition of land on which it is to be situated;
the costs of compliance with the conditions attached to planning consents and property rights;
the costs of third-party works upon which a project’s electricity solution’s operation depends;
project management costs;
itemised risk and contingency allowances;
costs relating to the procurement of itemised goods, services and works;
any other costs that are reasonably integral or relevant to the arrangement, construction, commissioning, procurement, operation or function of the project’s electricity solution.