# The Electricity (Early-Model Competitive Tenders for Onshore Transmission Licences) Regulations 2025, Regulation 35: Changes to delivery of documents or actions


(1) Paragraph (2) applies where a tender party determines that it is impracticable—
(a) for any document or notice which must be delivered to or published by the tender party in accordance with these Regulations to be delivered or published by the time, date or in the manner specified in accordance with these Regulations, or
(b) for any action which must be undertaken in accordance with these Regulations, to be completed by the time, date or in the manner specified.
(2) Where this paragraph applies, the tender party must give notice to a bidder, qualifying bidder, provisional preferred bidder, preferred bidder, reserve bidder or successful bidder, as the case may be, that—
(a) delivery or publication must be made by a different time or date or in a different manner, or
(b) the action must be completed by a different time or date or in a different manner.

---
Source: https://www.legislation.gov.uk/uksi/2025/446/regulation/35 (the official version)
Page: https://openlegislation.uk/electricity-early-model-competitive-tenders-for-onshore-transmission-licences-regulations-2025/regulation-35
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.