Regulation 6 Qualifying Projects
(1)
The delivery body must make a request in writing to the Authority if it wishes to commence an onshore transmission tender exercise in respect of a project that relates to the total system and to publish a notice in accordance with regulation 8(1).
(2)
(3)
A project that relates to the total system will be a qualifying project if the Authority is satisfied that each requirement specified in paragraph 1 of Schedule 1 is met.
(4)
The Authority may issue an information notice to require the delivery body or any other person to provide any other information it considers necessary in order to carry out its assessment in relation to paragraph 1 of Schedule 1.