# The Electricity (Early-Model Competitive Tenders for Onshore Transmission Licences) Regulations 2025, Regulation 7: Entry conditions in respect of qualifying projects


(1) In respect of a qualifying project, the Authority must, at a time determined by the Authority, notify the delivery body of—
(a) the information that the Authority requires in order to be satisfied that the entry conditions have been met in respect of that qualifying project, and
(b) the date by which each of the entry conditions must be met by the delivery body in respect of that qualifying project.
(2) The Authority may issue an information notice to require the delivery body to provide any other information it considers necessary in order to satisfy itself that the entry conditions specified in paragraph 1 of Schedule 2 have been met.
(3) The delivery body may issue an information notice to require any person excluding the Authority to provide any information it considers necessary in order to meet the entry conditions specified in paragraph 1 of Schedule 2.
(4) Where the Authority is satisfied that the entry conditions have been met in accordance with paragraph (1), it must give notice to that effect to the delivery body.

---
Source: https://www.legislation.gov.uk/uksi/2025/446/regulation/7 (the official version)