The events in this paragraph are—
(a) there are no bidders or qualifying bidders in respect of a qualifying project,
(b) a project fails to meet, or ceases to meet, any criterion of a relevant electricity project suitable for an early-model tender exercise pursuant to the Electricity (Criteria for Relevant Electricity Projects) (Transmission) Regulations 2024, and
(c) a qualifying project fails to meet, or ceases to meet, the entry conditions specified in paragraph 1 of Schedule 2, in accordance with regulation 7.

---