# The Electricity (Exemption from the Requirement for a Generation Licence) (Curen) (England and Wales) Order 2012, Article 3: Exemption from section 4(1)(a) of the Act


Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to Curen Limited in respect of Lynemouth Power Station for the period commencing on 6th December 2012 and ending on 31st March 2015.

---
Source: https://www.legislation.gov.uk/uksi/2012/2740/article/3 (the official version)
Page: https://openlegislation.uk/electricity-exemption-from-the-requirement-for-a-generation-licence-curen-england-and-wales-order-2012/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.